Renewing an old villa is one of the projects owners most often regret when done in the wrong order: new tiles broken months later to fix a pipe, premium paint peeling from untreated damp, or a budget that runs out halfway because a structural problem appears. This article sets out the complete plan in the right order, as we deliver it in Dammam, Khobar and Dhahran.

Step 1: Survey before any decision

Do not start with design or prices. Start with a survey:

  • Structure: cracks in slabs, columns and beams, visible rebar corrosion and spalling concrete.
  • Damp: rising from the ground in lower walls, coming through an expired roof membrane, or from leaking pipes.
  • Services: age and type of wiring, the distribution board, and pipe type (steel or PPR).
  • Waterproofing: condition of roof and bathroom waterproofing.

Where structural cracks or widespread corrosion appear, we recommend a structural report from an engineering office, costing SAR 1,500–4,500 per report, far cheaper than a wrong decision.

Step 2: Renovate or rebuild?

After the survey comes the biggest decision. Renovation is cheaper when the structure is sound or repairable and the problems are in waterproofing, services and finishes. Rebuilding may be better when corrosion is widespread in load-bearing elements, when you want a completely new layout or extra floors, or when renovation costs approach new-build costs.

For comparison: full renovation costs SAR 300–850 per m² built-up area, while a new build needs the structure (SAR 430–720 per m² built-up area) and then finishing (SAR 650–2,300 per m² built-up area).

Step 3: Plan and budget

List everything you want to change, then rank it:

  1. Essential: what stops the building deteriorating (waterproofing, rebar, leaks, unsafe wiring).
  2. Important: what improves daily life (bathrooms, kitchen, AC).
  3. Cosmetic: what can be deferred or upgraded later (décor, feature lighting).

An example full renovation of a 400 m² villa:

ItemQuantityEconomyMid-rangeLuxury
Full house or villa renovation400 m² built-up area160,000260,000340,000
Total (before VAT)160,000260,000340,000
Average per m²400650850

Calculated the same way as our online quote form, from the current price guide (SAR, before VAT, Eastern Province). Quantities are estimates confirmed at the free site visit.

Step 4: Repairs and services first

This order protects your investment:

  1. Strip-out and demolition of what will change.
  2. Structural repair: rebar and concrete treatment and crack injection.
  3. Damp treatment and waterproofing of roofs and bathrooms with flood testing.
  4. New services: electrics, plumbing, AC and data.
  5. Plaster and levelling over the new work.
ItemUnitEconomyMid-rangeLuxury
Rebar corrosion treatment & concrete repairm²150–220280360
Epoxy injection of structural crackslinear m80–130170220
Rising damp treatment (injection)linear m120–170210270
Roof insulation (membrane, PU foam or full system)m²30–55120180
Old wiring replacementpoint50–75100130
Old pipe replacement with PPRpoint180–250290360
Tile demolitionm²10–141722
Debris removaltruck load250–360430550

SAR before VAT, materials and labour, Eastern Province market. Prices update automatically from our price guide.

Step 5: Finishing and facades

Once everything beneath is sound, the enjoyable stage begins: floors, ceilings, paint, doors, bathrooms and kitchens, then facades. This is your chance to truly modernise: an open living area by removing a non-load-bearing wall, an open kitchen, layered ceilings with concealed lighting, and a modern stone or render facade.

Step 6: Handover and warranty

Accept the work against a written checklist: test every power and plumbing point, check falls and leaks, and review finishes room by room. Keep the written warranty on waterproofing, services and finishes.

Should you live there during works?

Partial renovation can be phased. For a full renovation, vacating shortens the programme considerably, protects the family from dust and noise, and often saves money overall.

Start with a survey

See our villa renovation and finishing service, and read old house renovation cost in the Eastern Province and treating wall damp for good; all prices are in our price guide.

Frequently asked questions

What is the first step in renovating an old villa?

A full survey of structure, damp, services and waterproofing before any design or pricing.

When is demolishing an old villa better than renovating?

When corrosion is widespread in load-bearing elements, you want a completely new layout, or renovation costs approach a new build.

How much does it cost to renovate an old villa?

Full renovation costs SAR 300–850 per m² built-up area; the actual cost is set by the survey.

Why are services done before finishing?

Because changing them afterwards means breaking new tiles and walls.

How long does villa renovation and finishing take?

Usually 3–6 months depending on size and scope.

Want a price for your own project? Get your quote now using the same method as this article, book a free site visit, or ask Sanad, our AI assistant.