Article contents
“Turnkey” is one of the most used and least clear terms in the finishing market. One contractor means everything including lighting and the kitchen; another means only tiles and paint. The result is disputes after signing and costs the owner never planned for. This article gives the complete list of what turnkey finishing should include and the terms to write into the contract.
Shell, completion and full finishing: what is the difference?
- Shell: concrete and blockwork only, with no plaster or services.
- Completion finishing: starts after plaster and rough-in and covers tiles, gypsum, paint, doors and fittings, at SAR 450–1,300 per m² built-up area.
- Full turnkey finishing: starts at shell and ends at move-in, at SAR 650–2,300 per m² built-up area for villas and SAR 550–1,750 per m² for apartments.
The complete list: what turnkey should include
Core works
- Internal and external plaster.
- Full electrical rough-in: wiring, boards, switches and sockets.
- Plumbing rough-in: supply, drainage and water heaters.
- AC rough-in: copper and drains, or ducts for concealed AC.
- Roof and bathroom waterproofing with flood testing, and thermal insulation.
Interior finishes
- Floors and skirting in every room.
- Bathroom and kitchen wall tiling.
- Gypsum ceilings to the approved design.
- Filler and paint for all walls and ceilings.
- Internal and main doors.
- Windows and aluminium.
- Sanitary ware, mixers and accessories.
- Kitchen cabinets and worktops.
- Lighting (spots and fittings as agreed).
External works and handover
- Facades: paint, stone or render profile.
- Courtyards, fences and gates.
- Final deep clean.
- Commissioning and testing of all systems.
Items to specify explicitly because contracts differ: the AC units themselves, kitchen appliances, curtains, feature lighting, CCTV, pools and landscaping.
Worked example: a 400 m² villa, turnkey
| Item | Quantity | Economy | Mid-range | Luxury |
|---|---|---|---|---|
| Full bathroom renovation (plumbing, waterproofing, tiles) | 7 bathroom (4–6 m²) | 80,500 | 140,000 | 224,000 |
| Ceramic & porcelain flooring supplied & laid | 400 m² | 36,000 | 76,000 | 152,000 |
| Internal plastering | 1,500 m² | 31,500 | 40,500 | 48,000 |
| Interior door | 22 door | 19,800 | 39,600 | 77,000 |
| Interior painting with full putty | 1,120 m² wall | 24,640 | 39,200 | 56,000 |
| Windows | 48 m² | 18,240 | 31,200 | 45,600 |
| Elastomeric exterior facade paint | 480 m² | 19,200 | 26,400 | 33,600 |
| Roof insulation (membrane, PU foam or full system) | 200 m² | 9,000 | 24,000 | 36,000 |
| Electrical point | 180 point | 15,300 | 23,400 | 30,600 |
| Flat gypsum board ceiling | 240 m² | 13,200 | 18,000 | 24,000 |
| External plastering | 480 m² | 12,000 | 15,360 | 18,240 |
| LED spotlight installed | 140 piece | 5,600 | 11,200 | 15,400 |
| Skirting | 280 linear m | 4,760 | 10,640 | 15,400 |
| Kitchen (cabinets & worktop, installed) | 4 linear m | 4,400 | 8,000 | 12,800 |
| Split AC first-fix (copper & drain) | 16 point | 3,680 | 6,080 | 8,000 |
| Kitchen first-fix (plumbing, electrics, ventilation) | 1 kitchen | 3,200 | 5,000 | 7,000 |
| Network / data point | 10 point | 1,000 | 1,500 | 2,000 |
| Total (before VAT) | 302,020 | 516,080 | 805,640 | |
| Average per m² | 755 | 1,290 | 2,014 |
Calculated the same way as our online quote form, from the current price guide (SAR, before VAT, Eastern Province). Quantities are estimates confirmed at the free site visit.
Contract terms that protect you
- A materials list by brand and model, or a set price band for each item.
- Duration and delay penalties.
- Payments tied to stages, not dates: after plaster, after services, after tiling, and so on.
- A change mechanism: how additions or changes are priced.
- Warranty: duration and scope, especially for waterproofing and services.
- Handover: a joint checklist before the final payment.
Key item prices
| Item | Unit | Economy | Mid-range | Luxury |
|---|---|---|---|---|
| Complete villa electrical first-fix | m² built-up area | 55–80 | 100 | 130 |
| Complete villa plumbing first-fix | m² built-up area | 50–70 | 90 | 115 |
| Internal plastering | m² | 18–23 | 27 | 32 |
| External plastering | m² | 22–28 | 32 | 38 |
| Ceramic & porcelain flooring supplied & laid | m² | 70–110 | 190 | 380 |
| Flat gypsum board ceiling | m² | 45–60 | 75 | 100 |
| Interior painting with full putty | m² wall | 18–26 | 35 | 50 |
| Interior door | door | 700–1,100 | 1,800 | 3,500 |
| Kitchen (cabinets & worktop, installed) | linear m | 900–1,300 | 2,000 | 3,200 |
SAR before VAT, materials and labour, Eastern Province market. Prices update automatically from our price guide.
Start with a clear offer
See our turnkey full finishing service, read villa finishing cost in Dammam, and find all prices in our price guide.
Frequently asked questions
What does turnkey mean in finishing?
The contractor takes the building as a shell and hands it over ready to live in, with all services, finishes, facades and cleaning per a written list in the contract.
What is the difference between completion and full finishing?
Completion starts after plaster and rough-in; full finishing starts at shell and includes plaster and services.
Does turnkey include AC units and appliances?
It varies by contract and must be written explicitly.
How should finishing contract payments be split?
Ideally tied to completed, inspected stages rather than fixed dates.
How much does turnkey villa finishing cost?
SAR 650–2,300 per m² built-up area depending on tier; the article includes an example for a 400 m² villa.
Want a price for your own project? Get your quote now using the same method as this article, book a free site visit, or ask Sanad, our AI assistant.