Opening a nursery, kindergarten or private school is both an educational and an investment project, and the first challenge is the building: build new, lease and convert a villa, or renew an existing school? This article covers the cost of fitting out and finishing educational buildings in Dammam, Khobar and Dhahran and the safety points to plan for from the start.

Important: licensing requirements differ by facility type (nursery, kindergarten, school) and licensing authority, and they change over time. Check the current requirements with the licensing authority before committing to a site; we design the works around them.

Converting a villa into a nursery: what changes?

Most small nurseries in the Eastern Province start in a leased villa. Conversion usually includes:

  • Re-planning rooms into classrooms, a nap room, a changing room and administration.
  • Enlarging toilets and fitting child-height toilets and basins.
  • Emergency exits, outward-opening doors and fire alarms as required.
  • Protecting stairs, windows and sharp corners.
  • Slip-resistant floors in classrooms and corridors.
  • A safe outdoor area with suitable surfacing and shades.

Worked example: a 400 m² learning building

A nursery or kindergarten of about 400 m² with classrooms, toilets and a playground:

ItemQuantityEconomyMid-rangeLuxury
Full bathroom renovation (plumbing, waterproofing, tiles)7 bathroom (4–6 m²)80,500140,000224,000
Interior door27 door24,30048,60094,500
Vinyl flooring for offices & clinics400 m²34,00044,00056,000
Internal plastering1,500 m²31,50040,50048,000
Interior painting with full putty1,120 m² wall24,64039,20056,000
Electrical point240 point20,40031,20040,800
Windows48 m²18,24031,20045,600
Suspended 60×60 tile ceiling for offices360 m²25,20030,60039,600
Car parking shades60 m²9,60014,40019,200
LED spotlight installed140 piece5,60011,20015,400
Skirting280 linear m4,76010,64015,400
Water-resistant WPC door7 door5,6008,05010,150
6 cm interlock paving120 m²6,0006,6007,800
Split AC first-fix (copper & drain)16 point3,6806,0808,000
Network / data point27 point2,7004,0505,400
Total (before VAT)296,720466,320685,850
Average per m²7421,1661,715

Calculated the same way as our online quote form, from the current price guide (SAR, before VAT, Eastern Province). Quantities are estimates confirmed at the free site visit.

For larger schools, an estimate for a 1,500 m² building:

ItemQuantityEconomyMid-rangeLuxury
Full bathroom renovation (plumbing, waterproofing, tiles)25 bathroom (4–6 m²)287,500500,000800,000
Interior door100 door90,000180,000350,000
Vinyl flooring for offices & clinics1,500 m²127,500165,000210,000
Internal plastering5,625 m²118,130151,880180,000
Interior painting with full putty4,200 m² wall92,400147,000210,000
Electrical point900 point76,500117,000153,000
Windows180 m²68,400117,000171,000
Suspended 60×60 tile ceiling for offices1,350 m²94,500114,750148,500
Car parking shades225 m²36,00054,00072,000
LED spotlight installed525 piece21,00042,00057,750
Skirting1,050 linear m17,85039,90057,750
Water-resistant WPC door25 door20,00028,75036,250
6 cm interlock paving450 m²22,50024,75029,250
Split AC first-fix (copper & drain)60 point13,80022,80030,000
Network / data point100 point10,00015,00020,000
Total (before VAT)1,096,0801,719,8302,525,500
Average per m²7311,1471,684

Calculated the same way as our online quote form, from the current price guide (SAR, before VAT, Eastern Province). Quantities are estimates confirmed at the free site visit.

Key item prices

ItemUnitEconomyMid-rangeLuxury
Vinyl flooring for offices & clinicsm²70–95110140
Suspended 60×60 tile ceiling for officesm²60–7585110
Interior painting with full puttym² wall18–263550
Interior doordoor700–1,1001,8003,500
Full bathroom renovation (plumbing, waterproofing, tiles)bathroom (4–6 m²)9,000–14,00020,00032,000
Split AC first-fix (copper & drain)point180–280380500
6 cm interlock pavingm²45–505565
Car parking shadesm²120–190240320
Artificial grass installedm²35–506580

SAR before VAT, materials and labour, Eastern Province market. Prices update automatically from our price guide.

Safety points worth the budget

  1. Floors: slip-resistant vinyl in classrooms and slip-resistant porcelain in toilets.
  2. Doors: finger guards, vision panels and outward-opening emergency doors.
  3. Stairs and windows: balustrades at a height that prevents climbing, and protected windows.
  4. Electrics: protected sockets out of children’s reach and emergency lighting.
  5. Playgrounds: impact-absorbing surfaces under play equipment and sun shades.

Summer renovation for operating schools

Operating schools usually need periodic renovation: painting, toilet repairs, AC renewal and leak repair. What matters most is the schedule: everything must finish before students return, so we plan before the holiday starts and procure materials in advance.

Start with the right plan

See our school and nursery finishing service, interlock paving for playgrounds, and gardens, pergolas and shades; all prices are in our price guide.

Frequently asked questions

How much does it cost to convert a villa into a nursery?

It depends on the villa's condition, size and scope of changes; this article includes a worked example for a 400 m² building in three tiers.

What are the requirements for a nursery building?

They vary by licensing authority and facility type and usually cover exits, safety, toilets and space; check them before committing to a site.

What is the best floor for a nursery?

Slip-resistant vinyl for classrooms, and impact-absorbing surfaces under playground equipment.

How long does a nursery fit-out take?

Converting a villa into a nursery usually takes 6–10 weeks depending on the scope of changes.

Do you renovate during the summer holiday?

Yes, on a written schedule that ends before the school year starts.

Want a price for your own project? Get your quote now using the same method as this article, book a free site visit, or ask Sanad, our AI assistant.