Opening a nursery, kindergarten or private school is both an educational and an investment project, and the first challenge is the building: build new, lease and convert a villa, or renew an existing school? This article covers the cost of fitting out and finishing educational buildings in Dammam, Khobar and Dhahran and the safety points to plan for from the start.
Important: licensing requirements differ by facility type (nursery, kindergarten, school) and licensing authority, and they change over time. Check the current requirements with the licensing authority before committing to a site; we design the works around them.
Converting a villa into a nursery: what changes?
Most small nurseries in the Eastern Province start in a leased villa. Conversion usually includes:
- Re-planning rooms into classrooms, a nap room, a changing room and administration.
- Enlarging toilets and fitting child-height toilets and basins.
- Emergency exits, outward-opening doors and fire alarms as required.
- Protecting stairs, windows and sharp corners.
- Slip-resistant floors in classrooms and corridors.
- A safe outdoor area with suitable surfacing and shades.
Worked example: a 400 m² learning building
A nursery or kindergarten of about 400 m² with classrooms, toilets and a playground:
| Item | Quantity | Economy | Mid-range | Luxury |
|---|---|---|---|---|
| Full bathroom renovation (plumbing, waterproofing, tiles) | 7 bathroom (4–6 m²) | 80,500 | 140,000 | 224,000 |
| Interior door | 27 door | 24,300 | 48,600 | 94,500 |
| Vinyl flooring for offices & clinics | 400 m² | 34,000 | 44,000 | 56,000 |
| Internal plastering | 1,500 m² | 31,500 | 40,500 | 48,000 |
| Interior painting with full putty | 1,120 m² wall | 24,640 | 39,200 | 56,000 |
| Electrical point | 240 point | 20,400 | 31,200 | 40,800 |
| Windows | 48 m² | 18,240 | 31,200 | 45,600 |
| Suspended 60×60 tile ceiling for offices | 360 m² | 25,200 | 30,600 | 39,600 |
| Car parking shades | 60 m² | 9,600 | 14,400 | 19,200 |
| LED spotlight installed | 140 piece | 5,600 | 11,200 | 15,400 |
| Skirting | 280 linear m | 4,760 | 10,640 | 15,400 |
| Water-resistant WPC door | 7 door | 5,600 | 8,050 | 10,150 |
| 6 cm interlock paving | 120 m² | 6,000 | 6,600 | 7,800 |
| Split AC first-fix (copper & drain) | 16 point | 3,680 | 6,080 | 8,000 |
| Network / data point | 27 point | 2,700 | 4,050 | 5,400 |
| Total (before VAT) | 296,720 | 466,320 | 685,850 | |
| Average per m² | 742 | 1,166 | 1,715 |
Calculated the same way as our online quote form, from the current price guide (SAR, before VAT, Eastern Province). Quantities are estimates confirmed at the free site visit.
For larger schools, an estimate for a 1,500 m² building:
| Item | Quantity | Economy | Mid-range | Luxury |
|---|---|---|---|---|
| Full bathroom renovation (plumbing, waterproofing, tiles) | 25 bathroom (4–6 m²) | 287,500 | 500,000 | 800,000 |
| Interior door | 100 door | 90,000 | 180,000 | 350,000 |
| Vinyl flooring for offices & clinics | 1,500 m² | 127,500 | 165,000 | 210,000 |
| Internal plastering | 5,625 m² | 118,130 | 151,880 | 180,000 |
| Interior painting with full putty | 4,200 m² wall | 92,400 | 147,000 | 210,000 |
| Electrical point | 900 point | 76,500 | 117,000 | 153,000 |
| Windows | 180 m² | 68,400 | 117,000 | 171,000 |
| Suspended 60×60 tile ceiling for offices | 1,350 m² | 94,500 | 114,750 | 148,500 |
| Car parking shades | 225 m² | 36,000 | 54,000 | 72,000 |
| LED spotlight installed | 525 piece | 21,000 | 42,000 | 57,750 |
| Skirting | 1,050 linear m | 17,850 | 39,900 | 57,750 |
| Water-resistant WPC door | 25 door | 20,000 | 28,750 | 36,250 |
| 6 cm interlock paving | 450 m² | 22,500 | 24,750 | 29,250 |
| Split AC first-fix (copper & drain) | 60 point | 13,800 | 22,800 | 30,000 |
| Network / data point | 100 point | 10,000 | 15,000 | 20,000 |
| Total (before VAT) | 1,096,080 | 1,719,830 | 2,525,500 | |
| Average per m² | 731 | 1,147 | 1,684 |
Calculated the same way as our online quote form, from the current price guide (SAR, before VAT, Eastern Province). Quantities are estimates confirmed at the free site visit.
Key item prices
| Item | Unit | Economy | Mid-range | Luxury |
|---|---|---|---|---|
| Vinyl flooring for offices & clinics | m² | 70–95 | 110 | 140 |
| Suspended 60×60 tile ceiling for offices | m² | 60–75 | 85 | 110 |
| Interior painting with full putty | m² wall | 18–26 | 35 | 50 |
| Interior door | door | 700–1,100 | 1,800 | 3,500 |
| Full bathroom renovation (plumbing, waterproofing, tiles) | bathroom (4–6 m²) | 9,000–14,000 | 20,000 | 32,000 |
| Split AC first-fix (copper & drain) | point | 180–280 | 380 | 500 |
| 6 cm interlock paving | m² | 45–50 | 55 | 65 |
| Car parking shades | m² | 120–190 | 240 | 320 |
| Artificial grass installed | m² | 35–50 | 65 | 80 |
SAR before VAT, materials and labour, Eastern Province market. Prices update automatically from our price guide.
Safety points worth the budget
- Floors: slip-resistant vinyl in classrooms and slip-resistant porcelain in toilets.
- Doors: finger guards, vision panels and outward-opening emergency doors.
- Stairs and windows: balustrades at a height that prevents climbing, and protected windows.
- Electrics: protected sockets out of children’s reach and emergency lighting.
- Playgrounds: impact-absorbing surfaces under play equipment and sun shades.
Summer renovation for operating schools
Operating schools usually need periodic renovation: painting, toilet repairs, AC renewal and leak repair. What matters most is the schedule: everything must finish before students return, so we plan before the holiday starts and procure materials in advance.
Start with the right plan
See our school and nursery finishing service, interlock paving for playgrounds, and gardens, pergolas and shades; all prices are in our price guide.
Frequently asked questions
How much does it cost to convert a villa into a nursery?
It depends on the villa's condition, size and scope of changes; this article includes a worked example for a 400 m² building in three tiers.
What are the requirements for a nursery building?
They vary by licensing authority and facility type and usually cover exits, safety, toilets and space; check them before committing to a site.
What is the best floor for a nursery?
Slip-resistant vinyl for classrooms, and impact-absorbing surfaces under playground equipment.
How long does a nursery fit-out take?
Converting a villa into a nursery usually takes 6–10 weeks depending on the scope of changes.
Do you renovate during the summer holiday?
Yes, on a written schedule that ends before the school year starts.